The development of the Damak–Chisapani Street (Falgunanda Marg), which has been beneath development for three decades, has ended up questionable once more after the end of contracts for the two areas of the street.Damodar Kunda: A conversion of religion and nature.This street, which has been a major plan in each decision in Jhapa, Ilam and Panchthar areas has confronted rehashed delays, inciting local people to raise their voices against the delay in its construction.Despite adequate budget allotments for the development of the street interfacing Damak in Jhapa withthe uneven areas of Ilam and Panchthar, the venture has been slowed down due to carelessness on the portion of the temporary workers.Damodar Kunda: A conversion of religio and nature.

Mangsebung Provincial Region Chairman Hemant Rai said that the unfinished street caused burdens to individuals in each storm season. He said that the provincial district had every so often designated reserves to evacuate avalanches and mud from the street. He said amid talks, temporary workers frequently guaranteed to total the work, but nothing was fulfilled. He said, “We have listened that the contracts have been ended and we do not know when the development work will resume.”

According to the Street Division Office in Damak, contracts were granted to broaden the track and blacktop the street in three areas six a long time back.

However, advance has been as it were around 50 per cent so distant. Out of the 33 kilometers from Damak to Chisapani, as it were almost two kilometers of the street has been tarred.

Gautam Kumar Dev, build and data officer of the Street Division Office in Damak, said that 60 per cent of the work had been completed on the to begin with area, which covers seven kilometers from Damak’s Zero Point. In this area, around two kilometers had been blacktopped.

Despite amplifying the due date more than five times, the work remains fragmented. Dev said, “The street is prepared for clearing but nonstop rain and different other reasons have deferred the work.”

Mahalaxmi–Kiratishwar JV was granted a contract for the to begin with area at Rs. 225 million on July 29, 2018, to total the development inside 30 months. This contract has not been ended.

Meanwhile, the contracts for the moment segment of 15 kilometers and the third area of 11 kilometers granted to Lumbini-Ganapati JV have been rejected. The contracts for these two segments were granted in Walk 2020.

There has been 60 per cent advance on the moment segment and 22 per cent on the third segment but blacktopping work has not however begun on either.

According to the Street Division Office, a modern prepare must be started for the development of the street after guaranteeing the essential assets and arrangements are underway in like manner.